Lien waiver tracking: how to stop chasing subs
A copyable lien waiver tracker, one draw worked through with numbers, the six checks to run on every waiver and a reminder schedule that ends the chasing.
The short answer. Keep one row for every payee in every draw, with the waiver type, the amount, the through date and whether it passed its checks. Ask for the conditional waiver when you ask for the pay application, and ask for the unconditional waiver the day the payment clears. Nothing gets paid on the next draw until last draw's unconditional is in and checked.
We make dailybuilt, which is not a lien waiver tool. The tracker, the worked draw and the reminder wording below work in a spreadsheet. Read it with that in mind.
How do you track lien waivers on a draw?
Track them per payee, per draw, in one list that everyone on the team reads from. The steps.
- List every payee in the draw. The general contractor, each subcontractor and each supplier being paid, plus any lower-tier sub or supplier your contract or lender asks for. Take the names from the contracts, not from memory.
- Add two rows for each payee. A conditional progress waiver for the money in this draw, and an unconditional progress waiver for the money paid in the last one.
- Send the requests with the pay application request. Name the amount, the through date and the form you need. A request that says "send your waiver" gets the wrong form back.
- Check each waiver the day it arrives. Amount, through date, payee, type, form and signature. The checks are below.
- Mark the row. Requested, received, passed, or failed with the reason.
- Chase on a schedule, not from memory. The cadence and the wording are below.
- Hold the payee's next payment until the row is clean. That one rule does more than any reminder.
A lien waiver tracker you can copy
Paste this into a spreadsheet. One row per waiver, not per payee.
| Draw | Payee | Tier | Waiver type | Amount | Through date | Form | Requested | Received | Check | Status |
|---|---|---|---|---|---|---|---|---|---|---|
| 4 | Ridge Framing Inc. | Sub | Conditional progress | $64,000.00 | Oct 31 | State form | Oct 30 | Nov 2 | Passed | Done |
| 3 | Ridge Framing Inc. | Sub | Unconditional progress | $52,000.00 | Sep 30 | State form | Oct 20 | Chasing |
Keep the amount and through date columns filled in before you send anything. They are what you check the signed waiver against, so they have to come from your own pay records, not from the waiver.
One draw worked through
This is an invented example, and the companies in it are not real. A builder is putting together draw 4 on a small commercial job. The pay applications run through October 31. Draw 3, through September 30, was funded on October 16 and paid out to five payees.
Draw 4 asks for $186,400.
| Payee | This draw (conditional) | Last draw paid (unconditional) |
|---|---|---|
| The builder, own work and fee | $38,900.00 | $41,300.00 |
| Ridge Framing Inc. | $64,000.00 | $52,000.00 |
| Volt Electric LLC | $27,500.00 | $18,000.00 |
| Cole Plumbing Co. | $31,000.00 | $22,500.00 |
| Northside Lumber | $25,000.00 | $30,200.00 |
| Total | $186,400.00 | $164,000.00 |
That is ten waivers. Four days before the package is due, eight are in. Running the checks finds three problems.
- Cole Plumbing's conditional says $13,000. The pay application says $31,000. Two digits swapped. Send it back. A waiver for less than the payment leaves the rest of the payment unwaived.
- Ridge Framing's unconditional for draw 3 isn't in. It was requested October 20, the day the payment cleared. The lender wants it before it funds draw 4, so Ridge's $64,000 can't go in the package until it arrives.
- Northside Lumber's unconditional is signed by "Northside Building Supply". The check went to Northside Lumber. Ask whether it is the same company. If it is, get the waiver reissued in the name on the contract. If it isn't, you have a waiver from the wrong party.
Volt Electric's conditional is still out but isn't due for four days, so that row is a reminder, not a problem. The package goes to the lender only when all ten rows read Passed.
What should you check on every lien waiver?
Check that the waiver matches your own records, because a signed waiver with the wrong number or name may not protect you. Six checks catch most problems.
- Amount. A conditional waiver should match what you are about to pay. An unconditional waiver should match what was actually paid, by check number if your state's form asks for one.
- Through date. It should match the end of the pay period you are paying for. A progress waiver covers work only through its date, so an earlier date leaves a gap.
- Payee. The name should match the contract and the check exactly. A sister company, a trade name or a misspelling is a question to ask, not a typo to ignore.
- Type. Conditional for money not yet paid, unconditional for money already received. Progress for a payment partway through, final for the last one.
- Form. In a state with statutory forms, use that state's form. More on that below.
- Signature and exceptions. Signed by someone who can bind the company, with any exceptions read. A waiver that lists a disputed amount or an unpaid extra waives less than it looks like.
When should you send lien waiver reminders?
Send them on fixed days tied to the draw date, so nobody has to remember. This cadence works for a monthly draw.
- With the pay application request. Ask for the conditional waiver for this period at the same time, with the amount and through date filled in.
- Three days before the package is due. One reminder to anyone whose conditional waiver is still out.
- The day before. A phone call, not an email.
- The day a payment clears. Ask for the unconditional waiver for exactly that amount.
- Seven days after. A reminder to anyone whose unconditional waiver is still out, saying their next payment waits for it.
Three messages cover most of it. Change the names and numbers.
Hi Dana, please send a conditional progress waiver for $31,000.00 through October 31 with your pay application, on the [state] statutory form. We need it by November 6 to get it into draw 4.
Hi Dana, your draw 3 payment of $22,500.00 cleared today. Please send an unconditional progress waiver for that amount through September 30.
Hi Dana, we still need your unconditional waiver for the $22,500.00 that cleared on October 20. We can't include your draw 4 payment in the package until it's in.
What do you do when a waiver comes back wrong?
Send it back the same day with the one thing that has to change, and ask for a new signed waiver rather than correcting it yourself. A waiver the signer didn't sign as written is one they can argue about later.
- Wrong amount or through date. Ask for a new waiver with the right figures, and send the figures again.
- Wrong form. Send the right form with the fields you already know filled in.
- Unconditional sent before the money arrived. Keep it, and still confirm the payment cleared before you mark the row. Then send them the conditional form for next time, because an unconditional waiver signed before payment puts them at risk.
- A payee who won't sign. Find out why before the draw date. It is usually a disputed change order or a late payment from you, and either one is better found now than by the lender.
Which states require a statutory lien waiver form?
California and Texas both do, and each sets out four forms in its statute. There is a conditional and an unconditional form for a progress payment, and the same two for a final payment. Beyond those two, the guides disagree, so check your state's own statute before you send a form.
- California. Civil Code sections 8132 to 8138 hold the four forms. Section 8124 says a waiver releases the owner and lender only if it follows one of them substantially and is signed, and a conditional waiver also needs evidence of payment, such as the claimant's endorsement on a check that the bank it was drawn on has paid, or the claimant's written acknowledgment of payment. Section 8126 says any other attempt to waive lien rights is void unless the claimant has been paid in full.
- Texas. Property Code section 53.284 holds the same four kinds of form, and a waiver that does not substantially comply with the right one is unenforceable. Section 53.283 says nobody may require an unconditional waiver until the claimant has actually received the payment. For original contracts signed on or after January 1, 2022, the waiver no longer has to be notarized.
- Florida. Section 713.20 sets out a progress form and a final form but does not require them. It says a waiver "may be" in those forms, that nobody may require a lienor to sign a different one, and that a waiver on another form is still enforceable on its own terms.
- Everywhere else. Levelset counts 12 states with required forms. The law firm Bradley counts 11. The difference is Florida, which Levelset includes with a footnote and Bradley leaves out. We have not read the other states' statutes, so treat either count as a starting point and read your own.
On California's unconditional forms, a notice warns the signer that the waiver is enforceable even if they haven't been paid, and that an unpaid claimant should use the conditional form instead.
Where software fits
Most of lien waiver tracking is the list and the chasing. Tools built for it, such as Built and Levelset, request waivers, collect signatures and show what is outstanding. For draws on several projects, see Rabbet vs Built vs Northspyre.
dailybuilt is not a lien waiver platform. It has no waiver or draw module, it does not read waivers or check their figures, and someone on your team still runs the six checks above. What it can do, on the Foundation plan, is hold the tracker and send the paper. A custom collection can hold each draw and a row for every waiver due. Documents and e-signature can send each payee the waiver to sign, with an audit trail and a sealed PDF of exactly what they signed. An automation can email a payee whose waiver is still out. The pricing page lists what each plan includes.
For the rest of a draw package, the construction draw request checklist lists the eight documents a lender checks, and the certificate of insurance checker covers the one that expires mid-job.
Questions people ask
What does California Civil Code section 8138 say?It sets out the unconditional waiver and release on final payment. The claimant says it has been paid in full for all its work on the job, except any disputed claims for extras it lists by amount, and the form warns that it is enforceable even if the claimant hasn't been paid. An unpaid claimant uses the conditional final form in section 8136 instead.
What is a lien waiver used for?A lien waiver is a signed statement from a contractor, subcontractor or supplier giving up its lien rights for a payment. It shows the owner and the lender that the money reached the people who did the work, and that the signer has given up its own right to lien the property for that amount.
How do you fill out a construction lien waiver?Use your state's statutory form if it has one. On California's forms you fill in the claimant, the customer, the job location, the owner and, for a progress waiver, the through date, then the check's maker, amount and payee on a conditional form. List any exceptions, and sign with the signer's title and date. Take the amount and through date from your pay records, not from the invoice.
What is the difference between a conditional and an unconditional lien waiver?A conditional waiver gives up lien rights for an amount only once that payment arrives, so it is safe to sign before you are paid. An unconditional waiver says the payment has already been received and gives up the rights when signed. On California's form that holds even if the money never came.
Do you need a lien waiver from every subcontractor?On most lender-funded draws, yes, from every payee being paid, though your loan agreement and contract set the actual list. Each draw usually carries conditional waivers for the money requested now and unconditional waivers for the money paid last time. Lower-tier subs and suppliers are added when your contract or your lender asks for them.
Sources
- California Civil Code section 8124
- California Civil Code section 8126
- California Civil Code section 8132, conditional progress
- California Civil Code section 8134, unconditional progress
- California Civil Code section 8136, conditional final
- California Civil Code section 8138, unconditional final
- California CSLB, conditional and unconditional waiver forms
- Texas Property Code section 53.283
- Texas Property Code section 53.284
- Texas H.B. 1456 (2011), enrolled text that added sections 53.283 and 53.284
- Texas H.B. 2237 (2021), enrolled text
- Florida Statutes section 713.20
- Levelset, 12 states with required lien waiver forms
- Bradley via JD Supra, is my lien waiver enforceable
- Levelset, requesting and tracking lien waivers
- Built, track waivers and payments
Keep reading
All postsConstruction draw schedule template, filled in
A copyable construction draw schedule filled in for a $600,000 build: six draws, 10% retainage, a running balance, a partial draw and the interest math.
Five jobs your team still does by hand
Chasing, retyping, checking, scheduling and following up. None is the work your business is paid for. What each one costs, with numbers that hold up.
R-410A install deadline removed: what EPA changed
EPA removed the install deadline for R-410A split systems built or imported before January 1, 2025, effective July 27, 2026. VRF still ends January 1, 2027.