Construction draw schedule template, filled in
A copyable construction draw schedule filled in for a $600,000 build: six draws, 10% retainage, a running balance, a partial draw and the interest math.

A draw schedule lists the stages of the job, what each stage is worth, the retainage held back from each payment and what is left to bill. The one below is filled in for a $600,000 build in six draws with 10% retainage: five draws pay $513,000 in total, $57,000 is held back, and the final draw pays the last $30,000 stage plus the $57,000. Copy the table, put in your own contract amount and stages, and keep it next to the budget your lender approved.
We make dailybuilt, which is not a draw platform. The template works in any spreadsheet, and every figure in it is worked out on the page. Read it with that in mind.
A construction draw schedule template you can copy
Paste this into Excel or Google Sheets. Column C is a percent of the contract, and every other number comes from it.
| Draw | Stage | % of contract | Scheduled amount | Retainage (10%) | Net paid | Total scheduled to date | Retainage held to date | Left to bill |
|---|---|---|---|---|---|---|---|---|
| 1 | Site work and foundation | 15% | $90,000 | $9,000 | $81,000 | $90,000 | $9,000 | $510,000 |
| 2 | Framing, roof and dry-in | 25% | $150,000 | $15,000 | $135,000 | $240,000 | $24,000 | $360,000 |
| 3 | Rough plumbing, electrical and HVAC | 20% | $120,000 | $12,000 | $108,000 | $360,000 | $36,000 | $240,000 |
| 4 | Insulation, drywall and interior trim | 20% | $120,000 | $12,000 | $108,000 | $480,000 | $48,000 | $120,000 |
| 5 | Finishes, fixtures and flooring | 15% | $90,000 | $9,000 | $81,000 | $570,000 | $57,000 | $30,000 |
| 6 | Final, punch list and retainage release | 5% | $30,000 | Releases $57,000 | $87,000 | $600,000 | $0 | $0 |
| Total | 100% | $600,000 | $600,000 |
The formulas, if you build it yourself.
- Scheduled amount is the contract amount times the stage's percent.
- Retainage is the scheduled amount times your retainage rate, from your contract.
- Net paid is the scheduled amount less retainage. On the final draw it is the last stage plus all the retainage held.
- Left to bill is the contract amount less the total scheduled to date. It is not the same as the "balance to finish, including retainage" figure in our draw schedule calculator, which also counts the retainage still held.
The stage split above is an example for a custom home. Lenders and contracts set their own stages. The OCC's handbook for bank examiners says a fixed payment at the end of each stage is normally used for residential and smaller commercial loans, and that commercial projects normally draw on a progress payment plan, with each request broken out by construction phase and cost category. Check the net paid column adds back to the contract amount. If it doesn't, a formula is wrong. If you'd rather not build it, the calculator does the same arithmetic, including change orders and a lower retainage rate later in the job.
What happens when a stage is only partly done?
The lender pays what the inspector says is in place, not what the schedule says. Say draw 2 is requested when framing is 80% complete.
- Inspected value is 80% of $150,000, so $120,000.
- Retainage at 10% is $12,000.
- Net paid on this draw is $108,000.
- The other $30,000 of the stage moves to the next draw. Less its $3,000 of retainage, that is $27,000 still to come, and $108,000 plus $27,000 is the $135,000 the schedule showed for the stage.
Keep a column for "inspected percent complete" next to the schedule, and bill from it. A line billed past the inspector's number is one of the reasons a draw comes back, as the construction draw request checklist covers.
How much interest does each draw cost?
If your loan charges interest only on what has been drawn, the schedule tells you what you're paying each month. Check your loan agreement, because the rate and the day count are set there. After draws 1 and 2 in the table, $216,000 has been paid out. At an example rate of 8% a year on a 365-day year, 30 days of interest on that is $216,000 × 8% × 30 ÷ 365, which is $1,420.27. After draw 4 it's on $432,000, twice as much: $432,000 × 8% × 30 ÷ 365 is $2,840.55.
That's why the order of the schedule matters. Money drawn early costs interest for longer, so a schedule that front-loads payments ahead of the work costs more than the same job billed as it goes.
What goes in each draw request?
The schedule says how much. The package proves the work was done and the people who did it were paid. Lenders typically ask for the pay application, invoices, a conditional lien waiver from each payee for this draw, an unconditional waiver for the last one, the inspection report and any approved change orders. The construction draw request checklist lists all eight documents and the errors that send a package back. Chasing those waivers is its own job, covered in lien waiver tracking.
Can you change a draw schedule once construction starts?
Yes, with the lender's approval. Two common reasons are a change order that adds or removes work, or one stage costing more than planned while another costs less.
Say the owner adds a $24,000 covered porch during framing. Add it as its own line, raise the contract to $624,000, and write the change order before anyone bills for it. Retainage applies to it like any other line: $2,400 held and $21,600 paid when the porch is billed in full. Left to bill goes up by $24,000 too. If instead framing runs $10,000 over and the interior comes in $10,000 under, the contract stays at $600,000 and you move the $10,000 between lines. That move is a reallocation. Get the lender's approval in writing before the next draw, because a budget line that runs over without one is a reason a draw comes back.
Draw schedule vs schedule of values vs pay application
They're three views of the same money.
- The draw schedule is the plan for when money is released, by stage or by month, agreed before the job starts.
- The schedule of values breaks the contract into line items with a value for each, so progress can be billed line by line.
- The pay application is the bill for one period. It reports percent complete on each line of the schedule of values, less retainage and what was paid before.
On a small residential job the draw schedule and the schedule of values are often the same table. On a commercial job the schedule of values is longer, and each pay application is a draw.
Where software fits
Draw platforms such as Rabbet, Built and Northspyre keep the budget, the schedule and each draw package for lenders and developers. The comparison of the three covers who each is for.
dailybuilt is not a draw platform. It has no draw or loan module, it does not read pay applications or check figures, and someone on your team still runs the numbers. What it can do, on the Foundation plan, is keep the paper in one place. A custom collection can hold each draw and its stage, amount and status. Documents and e-signature can send each payee its lien waiver to sign, with an audit trail. An automation can email a payee whose waiver is still out. The pricing page lists what each plan includes.
Questions people ask
Can I use Excel for a draw schedule template?Yes. The table above works in Excel or Google Sheets with four formulas, for scheduled amount, retainage, net paid and what is left to bill. Check that net paid adds back to the contract amount.
What is a typical construction loan draw schedule?There isn't one standard. The OCC's handbook says a standard payment plan for residential construction most commonly has five equal installments, paid as the work reaches agreed stages, and that commercial projects normally use a progress payment plan. Your lender's approved schedule is the one that counts.
Who approves payments in a construction draw schedule?On a construction loan, the lender. The OCC's handbook says the bank disburses after it reviews the draw request and independently confirms the progress of the work. On jobs billed on AIA pay applications, the architect certifies the amount first and may certify a different amount than was applied for.
Can a draw schedule be changed once construction begins?Yes, with the lender's written approval. A change order adds or removes a line and changes the contract amount. A reallocation moves money between lines and keeps the total the same.
What is retainage in a draw schedule?Retainage is the part of each payment held back until the job is finished. Your contract sets the rate. A lender can hold back as well: the OCC's handbook says banks on a progress payment plan normally keep 10 to 20 percent of each payment to cover cost overruns or unpaid bills. In the example it is 10%, and the $57,000 held over five draws is paid with the final draw.
Sources
- OCC Comptroller's Handbook, Commercial Real Estate Lending
- AIA, G702-1992 instructions and G703-1992 instructions
- Construction draw schedule calculator (dailybuilt)
- Construction draw request checklist (dailybuilt)
- Construction draw software compared: Rabbet vs Built vs Northspyre (dailybuilt)
- dailybuilt pricing
Keep reading
All postsLien waiver tracking: how to stop chasing subs
A copyable lien waiver tracker, one draw worked through with numbers, the six checks to run on every waiver and a reminder schedule that ends the chasing.
2026 NEC adoption by state: effective dates
The 2026 NEC is in effect in North Dakota (Jul 1, 2026), Colorado (Aug 1), Minnesota (Aug 17), Texas (Sep 1) and Oregon (Oct 1). Washington follows Dec 31.
Cabinet tariff rises to 50% on January 1, 2027
The tariff on imported kitchen cabinets and vanities goes from 25% to 50% on January 1, 2027, and upholstered furniture to 30%. What to do with open quotes.