Blog

2026 NEC adoption by state: effective dates

The 2026 NEC is in effect in North Dakota (Jul 1, 2026), Colorado (Aug 1), Minnesota (Aug 17), Texas (Sep 1) and Oregon (Oct 1). Washington follows Dec 31.

2026 NEC cover

This post covers 12 states, not all 50. In five of them the 2026 National Electrical Code is already in effect: North Dakota since July 1, 2026, Colorado since August 1, 2026, Minnesota since August 17, 2026, Texas since September 1, 2026, and Oregon since October 1, 2026. Washington's rule adopts it effective December 31, 2026. Every date below was read in the state's own rule or on its agency page on November 16, 2026. We did not check the other 38 states or the District of Columbia. If a state is not named here, that means we did not look, not that it has not adopted the code.

States where the 2026 NEC has an effective date

State Effective date Which jobs use it Agency
North Dakota July 1, 2026 The 2026 standards give the date and name no permit trigger State Electrical Board
Colorado August 1, 2026 Rule 1.5 sets the date and names no permit trigger State Electrical Board, 3 CCR 710-1
Minnesota August 17, 2026 Permits filed on or after August 17, 2026 Department of Labor and Industry, Board of Electricity
Texas September 1, 2026 All non-exempt electrical work from September 1, 2026 Department of Licensing and Regulation
Oregon October 1, 2026 2026 Oregon Electrical Specialty Code, based on the 2026 NEC Building Codes Division
Washington December 31, 2026 Permits issued on or after the adoption date, with two exceptions Department of Labor and Industries, WAC 296-46B-010

State by state, with the amendments worth knowing

North Dakota. The State Electrical Board's 2026 Laws, Rules, Wiring and Conveyance Standards are marked "Effective 07/01/2026". They refer throughout to the "NFPA 70 2026 edition, National Electrical Code (first version, printed in 2025)", and where the state standards and the NEC differ, the more restrictive requirement is the minimum. The introduction on the Board's web page still says 2023, so open the 2026 booklet itself. We did not find a statement of which permits fall under which edition. Ask the Board about a job permitted before July 1.

Colorado. The State Electrical Board held its rulemaking hearing on Rule 1.5 on May 27, 2026 and adopted the rule that day. The rule in the Code of Colorado Regulations now incorporates "the National Electrical Code, 2026 Edition" and says "The effective date shall be August 1, 2026." The "Draft Rules" link on the Board's own page still opens a draft that reads "2023 Edition", so read the rule on the Secretary of State's site. The rule does not say whether the test is the permit date or the work date. Ask the Board or your local inspector about a job that straddles August 1.

Minnesota. The Board of Electricity adopted the 2026 NEC with an effective date of August 17, 2026. Permits filed before that date must comply with the 2023 NEC. Permits filed on or after it must comply with the 2026 NEC. Licensing exams moved to the 2026 NEC beginning September 8, 2026.

Texas. The Commission of Licensing and Regulation voted on July 28, 2026 to adopt the 2026 NEC as the state electrical code, effective September 1, 2026, by amending 16 Texas Administrative Code §73.100. There is one exception: the Commission approved an amendment to section 210.8(F) so that GFCI protection is not required on outdoor dwelling HVAC outlets. State electrician exams have been on the 2026 NEC since September 1. TDLR's bulletin to the industry says a municipality may amend the state-adopted code but may not enforce a code below it, and that all state-licensed electricians must install to the 2026 NEC whether the work is inside city limits or out in the county.

Oregon. The 2026 Oregon Electrical Specialty Code took effect October 1, 2026. It is the 2026 NEC plus Oregon's Table 1-E, a 22-page table of amendments. Two entries to read first:

  • Oregon adopts seven Tentative Interim Amendments along with the code, including TIA 26-1 (680.21) and TIA 26-2 (690.12).
  • Oregon's section 90.4(D) says the code may require products that are not yet available when the code is adopted. In that case the authority having jurisdiction may permit products that comply with the most recent previous edition.

Washington. WAC 296-46B-010 reads: "Effective December 31, 2026, the 2026 edition of the National Electrical Code (NFPA 70-2026) including Annex A, B, and C is adopted in this chapter by reference and replaces the 2023 edition of the NFPA 70." Adopted standards apply when the issue date of the electrical permit is on or after the adoption date, except for:

  • New one- and two-family dwellings or multifamily dwellings where the building permit was issued before the adoption date.
  • New installations that need plan review, when the plans were received and accepted for review before the adoption date.

The same section says the Washington chapter controls where it conflicts with the NEC, so read the rest of chapter 296-46B for the state's own requirements.

A state that lists the 2026 NEC without a date

Wyoming. The Department of Fire Prevention and Electrical Safety lists the "2026 National Electrical Code" among the state's adopted codes. The page does not give an effective date for it. Call the department before you rely on a date from anywhere else.

States whose agency page still shows an earlier edition

These pages were read on November 16, 2026. A page can lag a rule change. We found that in three of the 12 states, where the adopting rule was newer than the agency's summary page. Confirm with the agency before you rely on any row here.

State Edition shown What the page says
South Dakota 2023 NEC Permits received on or after November 12, 2024 are inspected using the 2023 NEC
Nebraska 2023 NEC The State Electrical Division adopted the 2023 NEC beginning August 1, 2024
Georgia 2023 NEC Current state minimum codes list the NEC, 2023 Edition, with Georgia Amendments 2026
Vermont 2023 NEC Division of Fire Safety lists NFPA 70, 2023 edition, among primary adopted codes
Montana 2023 NEC The Building Codes Program lists the National Electrical Code, 2023 Edition, effective September 26, 2026. The electrical board page still says 2020 NEC

A worked example: which code is your job under?

Take a Minnesota contractor with two service upgrades sold days apart.

  • Job one. Permit filed Friday, August 14, 2026. That is before August 17, so the job is inspected to the 2023 NEC, even if the work is done in September.
  • Job two. Permit filed Monday, August 17, 2026. The job is under the 2026 NEC.

Three days on the calendar, two different code books. The same contractor's apprentice sitting for an exam had a little longer: exams switched on September 8, which is 22 days after August 17 (14 days to the end of August, plus 8).

Washington works on a different trigger. There the test is the issue date of the electrical permit, not the filing date. A commercial job that needs plan review stays under the 2023 NEC if the plans were received and accepted for review before December 31, 2026, even if the permit is issued in January.

What the dates have in common

All six states adopted the same edition. Oregon identifies it as the NEC approved as an American National Standard on September 9, 2025. The differences are in three places, and they are the three things to look up for any state:

  • The trigger. Permit filed (Minnesota), permit issued (Washington), or work performed on or after a date (Texas). Colorado's rule and North Dakota's standards give a date without naming a trigger, so ask.
  • The amendments. One GFCI exception in Texas. Twenty-two pages in Oregon.
  • The exam date. It can match the code date (Texas) or trail it (Minnesota).

If you bid work in more than one state, the estimate has to carry the right code year for each permit. That is the kind of detail that gets lost between the office and the truck. Our admin time cost calculator puts a number on what that back-and-forth costs each week.

Florida contractors have a different deadline this winter: see when the Florida Building Code 9th Edition takes effect.

States we did not check

We read agency pages for Minnesota, Texas, Oregon, Washington, Wyoming, Colorado, South Dakota, Nebraska, North Dakota, Georgia, Vermont and Montana. We did not check the other 38 states or the District of Columbia. Nothing in this post comes from a vendor adoption chart.

For a state not listed here, go to the state electrical board or building codes division and look for the rule that adopts the code by edition. That rule, plus any local amendments the state allows, is what an inspector enforces.

dailybuilt builds and runs the admin work for small companies. See how it works.

Questions people ask

When does NEC 2026 take effect?There is no single date. Each state adopts it by its own rule. Among the states we checked, the dates are July 1, 2026 (North Dakota), August 1, 2026 (Colorado), August 17, 2026 (Minnesota), September 1, 2026 (Texas), October 1, 2026 (Oregon) and December 31, 2026 (Washington).

When does NEC 2026 take effect in Texas?September 1, 2026. Texas adopted it as the state electrical code with one exception, an amendment to 210.8(F) on GFCI protection for outdoor dwelling HVAC outlets.

When does the 2026 NEC go into effect in Minnesota?It already has. Permits filed on or after August 17, 2026 must comply with the 2026 NEC, and licensing exams switched on September 8, 2026.

Has Colorado adopted the 2026 NEC?Yes. The State Electrical Board adopted it on May 27, 2026. Rule 1.5 in 3 CCR 710-1 incorporates the 2026 edition and sets the effective date as August 1, 2026.

Is there a 2026 NEC adoption map?We did not use one. Every date in this post comes from the state's own rule or agency page, and a map is only as current as its last update.

Can a city use an older code than the state?In Texas, no. TDLR says a municipality can amend the state-adopted code but cannot make a licensed contractor install to a standard below the 2026 NEC. Other states have their own rules on local amendments.

Sources

Keep reading

All posts

Book an intro call to scope what we build first.

Bring the software you run and the three jobs that take the most hours. Or create a workspace and run the platform yourself.

Every workspace starts with a 30-day free trial. You can export all of your data at any time.

Book an intro call

Free, 30 minutes. We reply within one business day to set a time.

or email info@dailybuilt.co