R-410A install deadline removed: what EPA changed
EPA removed the install deadline for R-410A split systems built or imported before January 1, 2025, effective July 27, 2026. VRF still ends January 1, 2027.

You can still install a new R-410A residential or light commercial split system, with no end date, as long as every specified component was manufactured in or imported into the United States before January 1, 2025. EPA removed the install deadline in a final rule published May 26, 2026 (91 FR 31284) and effective July 27, 2026. Variable refrigerant flow systems were left out. R-410A VRF equipment made or imported before January 1, 2026 must be installed before January 1, 2027.
This is the federal rule only. We did not check state refrigerant rules.
The deadlines, before and after the rule
| Equipment using a refrigerant with GWP of 700 or more | Before the May 2026 rule | Now |
|---|---|---|
| Residential and light commercial split systems, components made or imported before January 1, 2025 | Install before January 1, 2026 | No install deadline |
| The same systems, any component made or imported on or after January 1, 2025 | New installs prohibited | New installs prohibited |
| VRF systems, components made or imported before January 1, 2026 | Install before January 1, 2027 | Install before January 1, 2027 (unchanged) |
| VRF systems on a building permit issued before October 5, 2023 that specifies the refrigerant | Install before January 1, 2028 | Install before January 1, 2028 (unchanged) |
| Self-contained products such as window units | Manufacture and import ended January 1, 2025 | Unchanged |
R-410A is the refrigerant most contractors mean here. The rule is written by global warming potential, not by refrigerant name, so it reaches any regulated HFC or blend at 700 or above.
What EPA changed
The 2023 Technology Transitions rule stopped new installs of these systems on January 1, 2025. A December 26, 2023 interim rule gave equipment already in the pipeline one more year, to January 1, 2026. The May 2026 rule takes the date away. In EPA's words, it is "finalizing, as proposed, the removal of the deadline for installing residential and light commercial AC/HP systems when using equipment that was domestically manufactured or imported into the United States before January 1, 2025."
The regulation now reads, at 40 CFR 84.54(c)(1): new systems at a GWP of 700 or greater "may continue to be installed where all specified components of that system are manufactured or imported prior to January 1, 2025."
EPA's stated reason was stranded inventory. Distributors and contractors told the agency they still held a significant amount of R-410A equipment, that 2025 sales came in lower than forecast, and that the switch to R-454B happened faster than expected. EPA also noted that R-454B was hard to get in service cylinders in some regions during the changeover.
What still has a January 1, 2027 date
VRF. Commenters asked EPA to drop the VRF install date too. EPA answered that it "did not propose and is not extending the installation date for VRF equipment" and treated those comments as out of scope.
The regulation at 40 CFR 84.54(c)(2) allows a new VRF system at a GWP of 700 or greater in two cases:
- It is installed prior to January 1, 2027, and all specified components were manufactured or imported prior to January 1, 2026.
- It is installed prior to January 1, 2028, an approved building permit issued prior to October 5, 2023 specifies that refrigerant for the system, and all specified components were manufactured or imported prior to January 1, 2026.
"Installed" has a defined finish line. Under 40 CFR 84.54(e), assembling a system for the first time from used or new components counts as an installation "upon charging the system to full charge". A VRF system that is piped but not charged on December 31 has not been installed.
A worked example: the VRF calendar
A contractor has an R-410A VRF system on order for a small office. The condensing units were imported in October 2025. The building permit was issued in March 2026.
- The components predate January 1, 2026, so the equipment qualifies.
- The permit was issued after October 5, 2023, so the 2028 date does not apply.
- The system has to be charged to full charge before January 1, 2027.
From November 16, 2026 that leaves 45 days: 14 remaining in November plus 31 in December. If startup slips into January, the system cannot be installed as new under the federal rule.
Now change one fact. The same project's permit was issued in August 2023 and names R-410A for the system. The install date becomes December 31, 2027, which is 365 days later.
What a contractor can and cannot do now
You can:
- Install a new R-410A split system, ducted or ductless, mini-split or multi-split, when all specified components were made in or imported into the United States before January 1, 2025. There is no deadline.
- Replace the condensing unit on an existing R-410A system. EPA says this "is allowed and is not considered the installation of a new system", and that it made no change to how replacement condensing units are treated.
- Buy and sell condensing units for that purpose. EPA explains that condensing units are "specified components" and are not subject to the restrictions on manufacture, import, sale, distribution or export, so that existing equipment can keep being serviced.
- Install qualifying R-410A VRF before January 1, 2027.
You cannot:
- Install a new split system other than VRF at a GWP of 700 or above using a component manufactured or imported on or after January 1, 2025. That includes equipment built in Mexico or Canada before 2025 but imported afterward. EPA addressed this directly: such equipment "may not be installed as components of a new system."
- Build what is really a new system out of replacement parts. Assembling a system for the first time from used or new components is an installation. So is increasing the cooling capacity of an existing system. EPA also says that replacing the condensing unit and then later the indoor coil, or the coil and then the condensing unit, "would be considered the installation of a new system".
- Sell or distribute a product or specified component that is not labeled as 40 CFR 84.58 requires.
- Have a system installed that you could not install yourself. The prohibition covers anyone who has a system installed "through their position as a designer, owner, or operator of that system."
Self-contained products follow a separate track. Manufacture and import of self-contained residential and light commercial units at a GWP of 700 or more ended January 1, 2025, and the regulation ends their sale three years after that date, which is January 1, 2028.
What to keep on file
This section is our suggestion, not a recordkeeping requirement we found in the rule for installers. The exception turns on dates, so it helps to be able to show them. For each legacy system you install, consider keeping what shows when each component was manufactured or imported: the nameplate date, the distributor invoice, the serial number. Consider recording the date the system was charged too.
It is also good practice for quotes to say which refrigerant the equipment uses. If you are discounting R-410A inventory, tell the customer what they are buying and that the outdoor unit can be replaced later under the current rule, as long as the indoor coil is not replaced as well.
Tracking that per job takes office time. Our admin time cost calculator shows what the weekly paperwork costs, and if you run commercial vehicles across state lines, check whether the 2027 UCR fees apply to you. They are due before January 1.
dailybuilt builds and runs the admin work for small companies. See how it works.
Questions people ask
Can you still install 410A equipment in 2026?Yes, under the federal rule, for residential and light commercial split systems whose specified components were all manufactured in or imported into the United States before January 1, 2025. The install deadline was removed effective July 27, 2026.
Was the 410A ban lifted?Partly. EPA removed the install deadline for older inventory. It did not move the component cutoff: a new split system other than VRF still cannot use components made or imported on or after January 1, 2025.
Is R-410A banned?Not for servicing. The rule restricts new systems and new products. EPA says in the rule that HFCs "will continue to be available including to service existing equipment."
How long will R-410A be available?EPA does not give a date. It notes that under the AIM Act phasedown, HFC production and import continue from 2036 at 15 percent of the baseline indefinitely, and that "it may be many years until the installed base is zero" for R-410A equipment.
What is the R-410A deadline for VRF systems?Qualifying VRF equipment must be installed before January 1, 2027, or before January 1, 2028 when a building permit issued before October 5, 2023 specifies the refrigerant.
Can I replace just the outdoor unit on an R-410A system?Yes. EPA states that replacing a condensing unit on an existing system is allowed and is not a new installation. Replacing the indoor coil as well, even later, makes it a new system.
Sources
- Federal Register, Phasedown of Hydrofluorocarbons: Reconsideration of Certain Regulatory Requirements Promulgated Under the Technology Transitions Provisions of the AIM Act, 91 FR 31284, May 26, 2026
- 40 CFR 84.54, Restrictions on the use of hydrofluorocarbons (eCFR)
- EPA, Regulatory Actions for Technology Transitions
- EPA, Technology Transitions HFC Restrictions by Sector
Keep reading
All postsCabinet tariff rises to 50% on January 1, 2027
The tariff on imported kitchen cabinets and vanities goes from 25% to 50% on January 1, 2027, and upholstered furniture to 30%. What to do with open quotes.
UCR fees 2027: $55 for 0 to 2 trucks, up from $46
Unified Carrier Registration fees rise about 20% for 2027: $55 for 0 to 2 vehicles, $167 for 3 to 5, $333 for 6 to 20. Register before January 1, 2027.
2026 NEC adoption by state: effective dates
The 2026 NEC is in effect in North Dakota (Jul 1, 2026), Colorado (Aug 1), Minnesota (Aug 17), Texas (Sep 1) and Oregon (Oct 1). Washington follows Dec 31.