Construction draw schedule calculator with retainage

Enter the contract sum, the retainage rate and the stages of the work. See what each draw earns, what is held back and what gets paid, plus a payment application summary for any draw.

FreeNo sign-upRuns in your browser, nothing you type is sent to us

Contract

Draw stages

Stages add up to 100%

Schedule

Contract sum

$480,000.00

Retainage at completion

$38,400.00

Released after the final draw

DrawEarnedRetainagePayment
1. Foundation10% of contract, 10% held$48,000$4,800$43,200
2. Framing20% of contract, 10% held$96,000$9,600$86,400
3. Roof and dry-in15% of contract, 10% held$72,000$7,200$64,800
4. Rough-in plumbing, electrical and HVAC15% of contract, 10% held$72,000$7,200$64,800
5. Insulation and drywall15% of contract, 5% held$72,000$3,600$68,400
6. Finishes and fixtures15% of contract, 5% held$72,000$3,600$68,400
7. Final completion10% of contract, 5% held$48,000$2,400$45,600
Retainage release$38,400

Payment application

Contract sum to date
$480,000.00
Total completed to date
$216,000.00
Retainage to date
$21,600.00
Total earned less retainage
$194,400.00
Less previous payments
$129,600.00
Current payment due
$64,800.00
Balance to finish, including retainage
$285,600.00

The same lines as an AIA G702 application for payment. Retainage already held stays held when the rate drops; only later draws use the lower rate.

How to use it

  1. 1Enter the contract sum, any change orders and the retainage rate.
  2. 2List the draw stages with the percent of the contract each one covers.
  3. 3Read each payment, pick a draw for its application summary, and copy the schedule as CSV.

Questions

What is a construction draw schedule?

A plan that splits the contract sum into payments tied to stages of the work. The lender releases each draw once an inspection confirms the stage is done and the paperwork is complete.

What percentage should each draw be?

There is no single standard. The schedule in the calculator is an example. Use the percentages in your loan agreement or construction contract, and make sure they add up to 100%.

How is retainage calculated on a draw?

Multiply the amount earned on the draw by the retainage rate. At 10%, a $96,000 draw holds back $9,600 and pays $86,400. The held amount is paid when the contract says, usually at or after completion.

What does reducing retainage at 50% complete mean?

Some contracts drop the rate, for example from 10% to 5%, once half the work is done. Retainage already held stays held; only later draws use the lower rate. Your contract decides whether and when that happens.

What is the balance to finish, including retainage?

The contract sum minus everything earned so far less retainage. It is what is still to be paid, including the retainage being held, and matches the last line of an AIA G702.

A draw is only as good as its paperwork

Lenders fund a draw when the documents prove the stage is done and the people who did it were paid. The construction draw request checklist lists the eight documents a lender checks and the errors that send a draw back.

Find out which of these jobs we can take off your team

On a 30-minute intro call we go through the work your team does by hand and what we would build and run for you.

Book an intro call

Free, 30 minutes. We reply within one business day to set a time.

or email info@dailybuilt.co